The challenge

An operational technology (OT) wireless network solution provides the functionality required to enable sustainable equipment operation in an autonomous mining environment. We were engaged to deliver end-to-end management of the design, procurement, and implementation of optimising the wireless OT network at our client’s mine site to minimise the network impact on their autonomous fleet.

Our approach

We managed the project by working with our client’s vendor contractor partners to complete the engineering design, procurement, and commissioning of the network. We also engaged rigging vendors to deliver high risk riggings works onsite. Finally, we managed the procurement and storage of the equipment to optimise the project cost and schedule.

The results

The project has been successfully tracking on schedule and cost despite global supply chain issues that delayed the procurement of equipment.